PNGRB rewrites gas pipeline rules; proposes 14% returns to developers, shifts volume risk
The regulator said the existing bidding framework had threatened the financial viability of projects when actual gas flows fell short of projections
Account subscription benefits alongside Premium Stories, Editorials, Opinions and more.
Unlock these with Subscription
The View From India Looking at World Affairs from the Indian perspective.
First Day First Show News and reviews from the world of cinema and streaming.
Today's Cache Your download of the top 5 technology stories of the day.
Science For All The weekly newsletter from science writers takes the jargon out of science and puts the fun in!
Data Point Decoding the headlines with facts, figures, and numbers
THEdge At the cutting edge of education and careers
Health Matters Ramya Kannan writes to you on getting to good health, and staying there
Gender Agenda Stories from beyond the binary.
The Hindu On Books Books of the week, reviews, excerpts, new titles and features.
Updated - November 24, 2026 10:27 pm IST - New Delhi
Image for representational purpose only.
File | Photo Credit: The Hindu
India's oil and gas regulator has proposed a new framework for awarding natural gas pipeline projects that would guarantee developers a 14% post-tax return on equity while insulating them from the risk of lower-than-expected gas volumes, shifting the focus of competition from transportation tariffs to construction costs.
The Petroleum and Natural Gas Regulatory Board (PNGRB), in a concept paper and two sets of draft regulations dated November 23, 2026, has proposed selecting pipeline developers through competitive bidding based on the lowest quoted capital expenditure, replacing the existing approach under which bidders compete on tariffs and transportation capacity.
Under the proposed framework, developers of pipelines awarded through the capital expenditure-based bidding route would receive a fixed 14% post-tax return on the normative equity component of project cost over the pipeline's 40-year economic life.
Transportation tariffs, meanwhile, would be calculated on the basis of actual gas volumes carried, exposing shippers to higher per-unit charges if pipelines operate below capacity.
The regulator said the existing bidding framework, which encourages aggressive tariff or capacity commitments, had threatened the financial viability of projects when actual gas flows fell short of projections.
The proposed changes also draw on recommendations from two government-appointed high-level committees examining India's gas infrastructure requirements under Vision 2040 and competition in gas transmission and distribution.
Under the draft authorisation regulations, PNGRB would appoint separate independent agencies to assess demand and prepare a Detailed Feasibility Report (DFR) for each proposed pipeline.
The feasibility report would establish the project's technical specifications, scope, expected demand and estimated capital expenditure.
It would be placed in the public domain for consultation before the regulator issues the bidding documents.
Financial bids would then be ranked solely on the basis of the lowest capital expenditure quoted against the DFR estimate.
PNGRB would retain the authority to reject bids considered unreasonably high or low, with scope to relax such limits in the public interest, provided the reasons are recorded.
The proposed framework also removes the annual transportation-volume target for pipelines awarded through this route.
Under the existing provisions, failure to meet the prescribed target can result in forfeiture of the performance bond, which is set at 1% of project cost, subject to a maximum of ₹20 crore.
Developers would be required to commission projects within 36 months of authorisation, although extensions could be granted for delays beyond their control.
The draft also proposes increasing the additional capacity that must be made available to third parties under open access to 100% of the combined requirement, from the existing 33%.
The proposed tariff framework provides a separate mechanism for pipelines awarded through capital expenditure-based bidding.
The 14% post-tax return would be calculated on a normative equity base equivalent to 30% of the quoted project cost, assuming a standard debt-equity ratio of 70:30, irrespective of the developer's actual financing structure.
For example, a pipeline with a quoted capital cost of ₹10,000 crore would have a normative equity base of ₹3,000 crore on which the prescribed return would be calculated.
Normative debt would be repaid over 15 years following a three-year moratorium, through equal annual instalments.
Operating expenditure would be benchmarked at 2% of the quoted capital cost, with an annual escalation of 4.5%.
Fuel, employee costs and debt servicing would be accounted for separately under the proposed framework.
Tariffs would be determined using actual transportation volumes.
If gas flows exceed the higher of the regulator's projected volume or 75% of the pipeline's capacity, half of the additional volume-related benefit would be passed on to users through lower tariffs.
The framework seeks to provide developers with greater certainty on returns while linking the recovery of transportation costs to actual pipeline utilisation.
The concept paper proposes a tariff true-up every two years and sets the normative interest rate at the State Bank of India's one-year marginal cost of funds-based lending rate (MCLR).
The draft tariff regulations instead prescribe the benchmark plus one percentage point and provide for tariff reviews every five years, without incorporating the proposed two-year true-up in the relevant schedule.